Additional Generator being Added at the Data Center May 18-20

Monday, 18 May 08:15 CDT

May 18-20: UND is working with Caterpillar to commission the third generator being added to the NDUS Data Center. This work will cover the installation and testing of the PLC controls upgrade package for the CAT Paralleling switchgear. The NDUS Data Center will continue to operate normally during the commissioning.